Count Wall Blocks and Slab Rebar for a Workshop

Count blocks around a doorway

A workshop drawing shows a 20-foot wall, 8 feet high, with a 3-by-7-foot doorway. The wall covers 160 square feet and the opening removes 21, leaving 139 square feet of masonry. A nominal 16-by-8-inch block face includes the mortar joint and covers 128 square inches. Multiply 139 by 144 and divide by 128 to get 156.375 block equivalents.

Apply a 5% breakage allowance to that figure, then round up to order 165 blocks. If your mortar bag lists a yield of 20 installed blocks under the planned conditions, divide 156.375 by 20 and round up to 8 bags. The spare blocks stay on the pallet, so they use no mortar. Concrete Block Calculator

Read the slab bar schedule separately

Suppose a separate slab detail shows a single mat in a 20-by-12-foot rectangle. For this example the drawing gives a 12-inch maximum spacing, a 2-inch inset to each outer bar centerline, and 2 inches of clearance at each bar end. Use the dimensions on your own reinforcement schedule.

Across the 12-foot width, the first and last lengthwise bar centers are 140 inches apart. That takes 12 intervals to stay within 12 inches, hence 13 lengthwise bars. Each run is 236 inches long after deducting end clearance. In the other direction, a 236-inch centerline span requires 20 intervals and 21 widthwise bars, each 140 inches long. Rebar Calculator

Turn runs into a purchase quantity

The cut list calls for 13 lengths of 19 feet 8 inches and 21 lengths of 11 feet 8 inches. Both fit in 20-foot stock. Two of even the shorter cuts exceed one stock bar, so this plan takes 34 stock bars. A supplier quoting cut-to-length steel can also use the finished cut list. Where a run exceeds stock length, enter the scheduled lap and check splice locations against the drawing.